Al Habtoor Tower
Business Bay Al HabtoorDLD project 2656
The short answer
Al Habtoor Tower is active on the DLD register, completion date 31 Dec 2026. It was 90.01% built at DLD’s inspection on 31 Aug 2026. Its 216 home sales over Oct 2025–Sep 2026 registered at a median AED 3.4m, AED 2,749 per sq ft.
Completion dateSourceDLD project registerWindowcompletion dateFigureas the register lists itDatasales to 5 Oct 2026 · DLD register read 13 Oct 2026How it is worked out
on the DLD register
BuiltSourceDLD project registerFigure% built at DLD’s latest inspectionDatasales to 5 Oct 2026 · DLD register read 13 Oct 2026How it is worked out
DLD inspection, 31 Aug 2026
Median 1 BRSourceDLD registered salesWindowOct 2025–Sep 2026Based on136 salesFiguremedian price and median price per sq ft of home sales of this sizeDatasales to 5 Oct 2026How it is worked out
AED 2,853/sq ft · 136 sales
Median home priceSourceDLD registered salesWindowOct 2025–Sep 2026Based on216 salesFiguremedian of registered home sales, not an asking priceDatasales to 5 Oct 2026How it is worked out
216 home sales, Oct 2025–Sep 2026
Sales, 12 monthsSourceDLD registered salesWindowOct 2025–Sep 2026Based on216 salesFigureregistered sales of every property typeDatasales to 5 Oct 2026How it is worked out
−62% on Oct 2024–Sep 2025
Registered prices of 1-bedroom homes here, Oct 2025–Sep 2026
Lower quartile, median and upper quartile of 136 home sales; median size 1,122 sq ft.
The DLD project register
ActiveCompletion date on the DLD register: 31 Dec 2026
90.01% built at DLD’s inspection on 31 Aug 2026.
- DLD project number
- 2656
- Status
- Active
- Completion date
- 31 Dec 2026
- Start date
- 1 Oct 2022
- Registered
- 13 Jun 2023
- Developer
- Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co L.L.C) · DLD developer 1094
- Escrow account bank
- Dubai Islamic Bank
- Units
- 1,739
- Buildings
- 8: Str Regis Hotel Dubai, The Hotel Collection, Al Habtoor City, Al Habtoor Tennis Academy, Al Habtoor Tower, Amna Tower, Al Habtoor Boulevard and 2 more
Inspection history: 11 inspections on the register
| Inspection date | Built |
|---|---|
| 31 Aug 2026 | 90.01% |
| 5 May 2026 | 80.04% |
| 30 Jan 2026 | 71.3% |
| 14 Oct 2025 | 60.18% |
| 22 Aug 2025 | 52.5% |
| 24 Apr 2025 | 44.06% |
| 27 Sep 2024 | 28.92% |
| 18 Jul 2024 | 26.06% |
| 18 Apr 2024 | 23.01% |
| 15 Feb 2024 | 16.66% |
| 1 Jun 2023 | 10.13% |
Source: Dubai Land Department project register, read 13 Oct 2026. The register’s own figures, shown as it lists them.
Developer’s reply: none yet. Al Habtoor can send a reply about these figures; replies are checked before they’re published and never change a number. How developers reply
Statement ID S-2656-H1 · DLD register read 13 Oct 2026
Home prices by size
registered home sales, Oct 2025–Sep 2026| Size | Sales | Median price | Median AED /sq ft | Median size, sq ft |
|---|---|---|---|---|
| 1 BR | 136 | AED 3.1m | 2,853 | 1,122 |
| 2 BR | 69 | AED 4.0m | 2,536 | 1,537 |
| 3 BR | 11 | AED 5.8m | 2,520 | 2,283 |
Medians of registered flat and villa sales with no data-quality flag; a size with fewer than 5 sales shows no median.
Check an asking price
use the size on the sale contractEnter the size and the asking price to compare them with registered sales.
The size starts at the median registered size for that size here; use the size on your sale contract. Fees as listed on DLD’s Property Sale Registration page. Compare with other projects in the price check
Price against launch
median price per sq ft, homes| Size | Launch | Sales | Latest | Sales | Change |
|---|---|---|---|---|---|
| 1 BR | AED 2,692 | 94 | AED 2,710 | 9 | +1% |
| 2 BR | AED 2,888 | 31 | AED 2,528 | 8 | −12% |
Launch: first 90 days of registered sales of off-plan homes, 22 Aug 2023 to 19 Nov 2023. Latest: every home sale of that size, Jul–Sep 2026. Shown only where both have at least 5 sales.
Latest registered sales
All recent sales| Date | Type | Sq ft | Price | AED /sq ft | vs area |
|---|---|---|---|---|---|
| 21 Sep 2026 | Flat · 2 BR Off-plan | 1,445 | AED 3.8m | 2,623 | +8% |
| 17 Sep 2026 | Flat · 1 BR Off-plan | 1,001 | AED 2.8m | 2,832 | +15% |
| 17 Sep 2026 | Flat · 2 BR Off-plan | 2,024 | AED 4.9m | 2,434 | +0% |
| 8 Sep 2026 | Flat · 2 BR Off-plan | 1,547 | AED 3.6m | 2,337 | −4% |
| 20 Aug 2026 | Flat · 1 BR Off-plan | 1,003 | AED 2.9m | 2,860 | +16% |
| 17 Aug 2026 | Flat · 2 BR Off-plan | 1,466 | AED 3.9m | 2,687 | +10% |
| 17 Aug 2026 | Flat · 2 BR Off-plan | 1,464 | AED 3.9m | 2,636 | +8% |
| 4 Aug 2026 | Flat · 1 BR Off-plan | 1,019 | AED 2.4m | 2,312 | −6% |
| 4 Aug 2026 | Flat · 2 BR Off-plan | 2,016 | AED 4.9m | 2,429 | −0% |
| 29 Jul 2026 | Flat · 1 BR Off-plan | 950 | AED 2.3m | 2,389 | −3% |
Every type of sale, newest first; DLD publishes no time of day. Price per sq ft for homes only. “vs area”: against the median for that size in Business Bay, Oct 2025–Sep 2026.
Al Habtoor’s latest ads on Google
Al Habtoor isn’t running any ads on Facebook or Instagram right now. These are its 3 most recent Google ads (Search, YouTube and Display) shown in the UAE, newest first, from Al habtoor real estate in Google’s Ads Transparency Center on 20 Oct 2026. Prices and claims in ads are the developer’s, not checked against DLD records.
Business Bay market insights
Registered with DLD under the district Business Bay, 2019 to 5 Oct 2026.
Each point is the median price per square foot of the month’s registered home sales (flats and villas). A month with fewer than 10 home sales is left as a gap. Registered prices, not asking prices.
Most sold size
1 bedroom
Share of the home sales over Oct 2025–Sep 2026 that recorded a bedroom count
Sales a year
Full years only, registered sales of every type. 4,953 sales in 2026 to 5 Oct.
Off-plan share
57% of the 8,128 sales over Oct 2025–Sep 2026 were registered as off-plan, DLD’s own registration type.
The full record
every figure behind the summarySales by year and by month
| Year | Sales | Off-plan | Ready | Value | Median home price | Median AED /sq ft |
|---|---|---|---|---|---|---|
| 2023 | 166 | 166 | 0 | AED 506m | AED 2.5m | 2,744 |
| 2024 | 505 | 505 | 0 | AED 1.61bn | AED 2.6m | 2,612 |
| 2025 | 479 | 479 | 0 | AED 1.73bn | AED 3.4m | 2,597 |
| 2026 to 5 Oct | 154 | 154 | 0 | AED 553m | AED 3.4m | 2,732 |
Sales and value: registered sales of every property type since Jan 2019. Off-plan: DLD’s registration type; Ready: every other sale. Medians: home sales only, shown with 5 or more.
Every registered sale, all property types.
Other projects in Business Bay
8,128 sales were registered in Business Bay over Oct 2025–Sep 2026, with homes at a median AED 2,082 per sq ft over Jul–Sep 2026.
| Project | Developer | DLD register | Sales, Oct 2025–Sep 2026 | Median home price |
|---|---|---|---|---|
| Binghatti Aquarise | Binghatti | Due Oct 2026 | 602 | AED 2.0m |
| Binghatti Skyrise | Binghatti | Due Dec 2026 | 434 | AED 1.5m |
| Downtown Residences | Deyaar | Due Dec 2030 | 364 | AED 2.6m |
| Hq by Rove | Irth | Due Mar 2029 | 328 | — |
| Binghatti Skyhall | Binghatti | Due Aug 2026 | 232 | AED 1.4m |
| Peninsula Four | Select Group | Finished | 212 | AED 2.0m |
| One by Binghatti | Binghatti | Due May 2026 | 212 | AED 3.1m |
| Tiger Sky Tower | Tiger | No completion date | 174 | AED 3.1m |
| Peninsula Three | Select Group | Finished | 170 | AED 1.7m |
| Avarra by Palace | Emaar | Due Jun 2031 | 155 | AED 3.2m |
| DAMAC Towers by Paramount | DAMAC | Finished | 151 | AED 1.7m |
| Lumena Alta by Omniyat | Omniyat | Due Apr 2031 | 145 | — |
Median home price over Oct 2025–Sep 2026, shown with 5 or more home sales.
Other projects by Al Habtoor
| Project | Area | Completion date | Built | Sales, Oct 2025–Sep 2026 |
|---|---|---|---|---|
| Al Habtoor City | Business Bay | Finished | — | 77 |
| The Residences, Al Habtoor Grand | Dubai Marina | None listed | 35.3% | 28 |
| Arista One | Al Satwa | Finished | — | 5 |
More from Al Habtoor
Every Al Habtoor projectAl Habtoor City
Business Bay · Al Habtoor
Finished on the DLD register
The Residences, Al Habtoor Grand
Dubai Marina · Al Habtoor
Arista One
Al Satwa · Al Habtoor
Finished on the DLD register
Photos: Business Bay and the Dubai Water Canal by Sergei Gussev (Wikimedia Commons, CC BY 2.0); Dubai Marina by Norlando Pobre (Wikimedia Commons, CC BY 2.0); Towers under construction, Dubai by Leandro Neumann Ciuffo (Wikimedia Commons, CC BY 2.0). Resized and cropped.
More projects in Business Bay
Everything in Business BayBinghatti Aquarise
Business Bay · Binghatti
Binghatti Skyrise
Business Bay · Binghatti
Downtown Residences
Business Bay · Deyaar
Binghatti Skyhall
Business Bay · Binghatti
Peninsula Four
Business Bay · Select Group
Finished on the DLD register
Photo: Business Bay and the Dubai Water Canal by Sergei Gussev (Wikimedia Commons, CC BY 2.0). Resized and cropped.
Before you buy a home in Al Habtoor Tower
About Al Habtoor Tower
Al Habtoor Tower is a Al Habtoor project in Business Bay, Dubai, registered with the Dubai Land Department as project 2656 by Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co L.L.C). The register lists it as active, with a completion date of 31 Dec 2026, 90.01% built at DLD’s inspection on 31 Aug 2026.
1,304 sales have been registered since Jan 2019, the first on 22 Aug 2023, 216 of them over Oct 2025–Sep 2026. Over those twelve months its 216 home sales registered at a median AED 3.4m. These are prices buyers paid, recorded at registration, not asking prices.
By sales since Jan 2019 it is 7th of the 140 projects with a registered sale in Business Bay, and 2nd of Al Habtoor’s 4.
Questions about Al Habtoor Tower
When will Al Habtoor Tower be finished?
The DLD register lists a completion date of 31 Dec 2026. It was 90.01% built at DLD’s inspection on 31 Aug 2026. These are the register’s own figures, read 13 Oct 2026; we don’t forecast a finish.
Is Al Habtoor Tower finished?
No. The DLD register lists it as active, 90.01% built at the inspection on 31 Aug 2026.
What do homes in Al Habtoor Tower sell for?
1 BR: a median AED 3.1m, AED 2,853 per sq ft, from 136 sales; 2 BR: a median AED 4.0m, AED 2,536 per sq ft, from 69 sales; 3 BR: a median AED 5.8m, AED 2,520 per sq ft, from 11 sales. Registered home sales over Oct 2025–Sep 2026, not asking prices.
How many sales has Al Habtoor Tower had?
1,304 sales registered with the Dubai Land Department since Jan 2019, 216 of them over Oct 2025–Sep 2026.
Who is the developer of Al Habtoor Tower?
The DLD register lists Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co L.L.C), DLD developer number 1094, which we group under Al Habtoor.
Where is Al Habtoor Tower?
In Business Bay, Dubai. The Dubai Land Department registers its sales under the district Business Bay. Homes there registered at a median AED 2,082 per sq ft over Jul–Sep 2026.
Which escrow account does DLD list for Al Habtoor Tower?
The DLD project register lists an escrow account with Dubai Islamic Bank for Al Habtoor Tower.
Cite this page
Al Habtoor Tower, Business Bay. Real Estate IQ, from DLD registered sales to 5 Oct 2026 and the DLD project register read 13 Oct 2026. dubairealestateiq.com/project/al-habtoor-tower
Sources: Dubai Land Department open data, registered sales to 5 Oct 2026, via Dubai Real Estate Data (CC BY 4.0), processed by Real Estate IQ; DLD project register, read 13 Oct 2026. Registered prices, not asking prices or valuations. How the figures are worked out.
Read next
GuideHow to check a Dubai off-plan project’s completion date
GuideAsking price or registered price: how to check a quote
TrackerActive projects on the DLD register, with their completion datesPhotos: Towers under construction, Dubai by Leandro Neumann Ciuffo (Wikimedia Commons, CC BY 2.0); Dubai Marina at night by Gfilip (Wikimedia Commons, CC BY-SA 4.0); Dubai skyline at dusk by imran shahabuddin (Wikimedia Commons, CC BY 2.0). Resized and cropped.