Off-plan · 6 min read · figures from DLD data to 2 Nov 2026

How to check a Dubai off-plan project’s completion date

Three steps with the Dubai Land Department’s own figures. No developer brochure needed.

Towers under construction with cranes on the Dubai waterfront. Photo: Leandro Neumann Ciuffo, Wikimedia Commons, CC BY 2.0, resized and cropped
Photo creditTowers under construction with cranes on the Dubai waterfront. Photo: Leandro Neumann Ciuffo, Wikimedia Commons, CC BY 2.0, resized and cropped

The short answer

The Dubai Land Department’s project register lists each off-plan project’s completion date and, after every DLD inspection, how much of it is built. Check both on the project’s page, note the date of the latest inspection, and compare them with the date in your sale contract.

Published 5 Oct 2026 · figures from DLD data to 2 Nov 2026, updated 18 Nov 2026

The Dubai Land Department’s project register lists off-plan projects with their completion date and, after DLD’s site inspections, how much of each is built. Those two figures are what to hold a brochure and a contract up against.

1. Find the completion date on the register

Search the project and the date is at the top of its page, with the date the register was read. It can differ from the date in a brochure, and the register shows only the current date, not earlier ones.

2. Read how much is built, and when

The % built comes from DLD’s inspections, and each project page lists them with their dates. Check the date of the latest one: the site may have moved on since.

3. Hold it up against your contract

Take Binghatti Skyrise. The register gives a start date of 15 Oct 2024 and a completion date of 31 Dec 2026. It was 35.89% built at DLD’s inspection on 22 Oct 2026 (register read 18 Nov 2026).

Your sale contract has its own completion date and says what happens if the project finishes after it. If the register’s date differs from it, or has passed while the project is still active, ask the developer in writing for the current schedule. A past date on its own doesn’t mean a project is late: the register shows the date DLD currently holds, which can change and can take time to update (DLD, Real Estate Project Status).

How often DLD inspects

The % built only changes when DLD inspects. Across the 1,347 active projects with at least two inspections on the register, the middle gap between the last two was 127 days, about 4 months. So a figure can be several months old: check the inspection date beside it before you read much into it.

Every project due this year, in one place

The register lists 244 active projects with a completion date in 2026. The off-plan tracker lists every active project with its completion date and % built, and you can filter it by area, developer and completion year.

Questions to ask the developer

  • What is the current construction schedule, and has the completion date on the register changed?
  • Which escrow account do my payments go into? Project pages show the escrow account DLD lists for the project, where it lists one.
  • What does my sale contract say happens if the project finishes after the contract date?

Get The weekly

The weekly: projects whose completion date or % built changed on the DLD register, and those that finished.

Projects to look at

Dubai, general view

Azizi Venice 14

Madinat Al Mataar · Azizi

Due May 2026DLD register
Built30%
Median home price, Nov 2025–Oct 2026AED 650k
2,042 sales, Nov 2025–Oct 2026
Dubai, general view

Binghatti Vintage

Majan · Binghatti

Due Mar 2027DLD register
Built11%
Median home price, Nov 2025–Oct 2026AED 710k
1,526 sales, Nov 2025–Oct 2026
Dubai, general view

DAMAC Lagoons - Valencia

Al Hebiah Fifth · DAMAC

Due Feb 2028DLD register
Built5%
Median home price, Nov 2025–Oct 2026AED 789k
1,359 sales, Nov 2025–Oct 2026

Photo: Towers under construction, Dubai by Leandro Neumann Ciuffo (Wikimedia Commons, CC BY 2.0). Resized and cropped.

Questions

How often is the % built updated?

Each time the Dubai Land Department inspects the site. Every project page lists the inspections with their dates, so check how recent the latest one is.

What does Finished mean on the register?

The Dubai Land Department has marked the project as complete. The date it lists is the completion date on its register.

Where do I see every project due this year?

The off-plan tracker lists every active project on the DLD register with its completion date and % built, filterable by area, developer and year.

Where does the completion date come from?

From the Dubai Land Department’s project register. Each project page shows it with the date the register was read.

Does a past completion date mean the project is late?

Not by itself. The register shows the date DLD currently holds, which can change and can take time to update. Ask the developer for the current schedule and check your contract.

Cite this page

How to check a Dubai off-plan project’s completion date. Real Estate IQ, 18 Nov 2026. dubairealestateiq.com/guides/check-handover

Sources: Dubai Land Department open data, registered sales to 2 Nov 2026, via Dubai Real Estate Data (CC BY 4.0), processed by Real Estate IQ; DLD project register, read 18 Nov 2026. Registered prices, not asking prices or valuations. How the figures are worked out.