Jumeirah Village Triangle · DLD district Al Barsha South Fifth Object 1DLD project 4212
Towers under construction with cranes on the Dubai waterfront. A general view of Dubai, not this projectPhoto: Leandro Neumann Ciuffo, Wikimedia Commons, CC BY 2.0, resized and cropped
A drawing, not this building: 4.16% built at DLD’s inspection on 9 Nov 2026
The short answer
Elaris Axis is active on the DLD register, completion date 30 Nov 2028. It was 4.16% built at DLD’s inspection on 9 Nov 2026.
Completion dateSourceDLD project registerWindowcompletion dateFigureas the register lists itDatasales to 2 Nov 2026 · DLD register read 18 Nov 2026How it is worked out
30 Nov 2028
on the DLD register
BuiltSourceDLD project registerFigure% built at DLD’s latest inspectionDatasales to 2 Nov 2026 · DLD register read 18 Nov 2026How it is worked out
4.2%
DLD inspection, 9 Nov 2026
Home salesSourceDLD registered salesWindowNov 2025–Oct 2026Based on3 salesFigureflats and villas, no data-quality flagDatasales to 2 Nov 2026How it is worked out
3
Nov 2025–Oct 2026
Median home priceSourceDLD registered salesWindowNov 2025–Oct 2026Based on3 salesFiguremedian of registered home sales, not an asking priceDatasales to 2 Nov 2026Fewer than 5 sales: no median shownHow it is worked out
—
3 home sales, Nov 2025–Oct 2026
Sales, 12 monthsSourceDLD registered salesWindowNov 2025–Oct 2026Based on9 salesFigureregistered sales of every property typeDatasales to 2 Nov 2026How it is worked out
9
Nov 2025–Oct 2026
The DLD project register
Active
Completion date on the DLD register: 30 Nov 2028
4.16% built at DLD’s inspection on 9 Nov 2026.
Started10 Jan 20264.2% builtinspection 9 Nov 2026Completion30 Nov 2028
Built, at DLD’s latest inspection4.16%
DLD project number
4212
Status
Active
Completion date
30 Nov 2028
Start date
10 Jan 2026
Registered
24 Sep 2026
Developer
Object One Real Estate Development L.L.C · DLD developer 1579
Escrow account bank
Abu Dhabi Islamic Bank
Units
171
Buildings
1: Elaris Axis
Inspection history: 3 inspections on the register
Inspection date
Built
9 Nov 2026
4.16%
12 Oct 2026
2.18%
11 Nov 2025
0%
Source: Dubai Land Department project register, read 18 Nov 2026. The register’s own figures, shown as it lists them.
Developer’s reply: none yet. Object 1 can send a reply about these figures; replies are checked before they’re published and never change a number. How developers reply
Statement ID S-4212-H1 · DLD register read 18 Nov 2026
Home prices by size
registered home sales, Nov 2025–Oct 2026
Size
Sales
Median price
Median AED /sq ft
Median size, sq ft
1 BR
3 · fewer than 5
—
—
—
Medians of registered flat and villa sales with no data-quality flag; a size with fewer than 5 sales shows no median.
Every type of sale, newest first; DLD publishes no time of day. Price per sq ft for homes only. “vs area”: against the median for that size in Jumeirah Village Triangle, Nov 2025–Oct 2026.
Object 1’s newest ads
None of Object 1’s 14 running ads names Elaris Axis; these are the newest, from Meta’s Ad Library on 18 Nov 2026. Prices and claims in ads are the developer’s, not checked against DLD records.
Construction continues at ALTA V1EW Skyhomes in Jumeirah Village Circle.
Inspired by light, space, and nature, the project introduces a new perspective on elevated living, combining striking architecture, panoramic views, and eco-conscious design.
Step by step, this vision is coming to life.
Shaping the future of UAE real estate through vision, expertise, and leadership.
At the Real Estate Leaders Summit 2026 in Dubai, our Managing Director, Faris Al Khattab, joined fellow industry leaders for a panel discussion on Balancing Supply & Demand, sharing insights into the market’s evolving dynamics and future opportunities.
Which Dubai district deserves your attention right now?
With strong sales activity, growing demand, and rising rental rates, Dubai Land Residence Complex is a location worth watching.
Discover what makes this district so promising as Object 1 prepares to introduce a new luxury project here.
Coming soon…
Şu anda Dubai’de hangi bölgeye dikkat etmelisiniz?
Güçlü satış performansı, artan talep ve yükselen kira getirileriyle Dubai Land Residence Complex (DLRC), yakından takip edilmesi gereken bölgelerden biri.
Object 1’in burada hayata geçirmeye hazırlandığı yeni lüks projesiyle birlikte, bu bölgeyi yatırım açısından bu kadar cazip kılan özellikleri keşfetmek için takipte kalın.
Lansman Çok yakında...
Each point is the median price per square foot of the month’s registered home sales (flats and villas). A month with fewer than 10 home sales is left as a gap. Registered prices, not asking prices.
Most sold size
1 bedroom
33%Studio
50%1
15%2
2%3
0%4
Share of the home sales over Nov 2025–Oct 2026 that recorded a bedroom count
Sales a year
5,303 sales2025+1686%on 2019
Full years only, registered sales of every type. 2,475 sales in 2026 to 2 Nov.
Off-plan share
83% of the 3,875 sales over Nov 2025–Oct 2026 were registered as off-plan, DLD’s own registration type.
The full record
every figure behind the summary
Sales by year and by month
Year
Sales
Off-plan
Ready
Value
Median home price
Median AED /sq ft
2026 to 2 Nov
9
9
0
AED 42.1m
—
—
Sales and value: registered sales of every property type since Jan 2019. Off-plan: DLD’s registration type; Ready: every other sale. Medians: home sales only, shown with 5 or more.
Other projects in Jumeirah Village Triangle
3,875 sales were registered in Jumeirah Village Triangle over Nov 2025–Oct 2026, with homes at a median AED 1,584 per sq ft over Aug–Oct 2026.
Elaris Axis is a Object 1 project in Jumeirah Village Triangle, Dubai, registered with the Dubai Land Department as project 4212 by Object One Real Estate Development L.L.C. The register lists it as active, with a completion date of 30 Nov 2028, 4.16% built at DLD’s inspection on 9 Nov 2026.
9 sales have been registered since Jan 2019, the first on 9 Oct 2026, 9 of them over Nov 2025–Oct 2026. These are prices buyers paid, recorded at registration, not asking prices.
By sales since Jan 2019 it is 62nd of the 66 projects with a registered sale in Jumeirah Village Triangle, and 15th of Object 1’s 15.
Questions about Elaris Axis
When will Elaris Axis be finished?
The DLD register lists a completion date of 30 Nov 2028. It was 4.16% built at DLD’s inspection on 9 Nov 2026. These are the register’s own figures, read 18 Nov 2026; we don’t forecast a finish.
Is Elaris Axis finished?
No. The DLD register lists it as active, 4.16% built at the inspection on 9 Nov 2026.
How many sales has Elaris Axis had?
9 sales registered with the Dubai Land Department since Jan 2019, 9 of them over Nov 2025–Oct 2026.
Who is the developer of Elaris Axis?
The DLD register lists Object One Real Estate Development L.L.C, DLD developer number 1579, which we group under Object 1.
Where is Elaris Axis?
In Jumeirah Village Triangle, Dubai. The Dubai Land Department registers its sales under the district Al Barsha South Fifth. Homes there registered at a median AED 1,584 per sq ft over Aug–Oct 2026.
Which escrow account does DLD list for Elaris Axis?
The DLD project register lists an escrow account with Abu Dhabi Islamic Bank for Elaris Axis.
Cite this page
Elaris Axis, Jumeirah Village Triangle. Real Estate IQ, from DLD registered sales to 2 Nov 2026 and the DLD project register read 18 Nov 2026. dubairealestateiq.com/project/elaris-axis