The short answer
DAMAC Islands - Bali 1 is active on the DLD register, completion date 31 Dec 2028. It was 2.79% built at DLD’s inspection on 4 May 2026.
Completion dateSourceDLD project registerWindowcompletion dateFigureas the register lists itDatasales to 5 Oct 2026 · DLD register read 13 Oct 2026How it is worked out
on the DLD register
BuiltSourceDLD project registerFigure% built at DLD’s latest inspectionDatasales to 5 Oct 2026 · DLD register read 13 Oct 2026How it is worked out
DLD inspection, 4 May 2026
Home salesSourceDLD registered salesWindowOct 2025–Sep 2026Based on0 salesFigureflats and villas, no data-quality flagDatasales to 5 Oct 2026How it is worked out
Oct 2025–Sep 2026
Median home priceSourceDLD registered salesWindowOct 2025–Sep 2026Based on0 salesFiguremedian of registered home sales, not an asking priceDatasales to 5 Oct 2026Fewer than 5 sales: no median shownHow it is worked out
0 home sales, Oct 2025–Sep 2026
Sales, 12 monthsSourceDLD registered salesWindowOct 2025–Sep 2026Based on16 salesFigureregistered sales of every property typeDatasales to 5 Oct 2026How it is worked out
−94% on Oct 2024–Sep 2025
The DLD project register
Active2.79% built at DLD’s inspection on 4 May 2026.
| Inspection date | Built |
|---|---|
| 4 May 2026 | 2.79% |
| 14 Jul 2025 | 0.24% |
| 6 Jan 2025 | 0% |
Source: Dubai Land Department project register, read 13 Oct 2026. The register’s own figures, shown as it lists them.
Developer’s reply: none yet. DAMAC can send a reply about these figures; replies are checked before they’re published and never change a number. How developers reply
Statement ID S-3475-H1 · DLD register read 13 Oct 2026
| Date | Type | Sq ft | Price | AED /sq ft | vs area |
|---|---|---|---|---|---|
| 1 Jul 2026 | Land Ready | 1,550 | AED 2.4m | — | — |
| 19 Jun 2026 | Land Ready | 1,550 | AED 2.1m | — | — |
| 8 May 2026 | Land Ready | 6,161 | AED 9.0m | — | — |
| 18 Feb 2026 | Land Ready | 1,550 | AED 2.5m | — | — |
| 11 Feb 2026 | Land Ready | 1,550 | AED 2.5m | — | — |
| 27 Jan 2026 | Land Ready | 1,550 | AED 2.5m | — | — |
| 21 Jan 2026 | Land Ready | 1,550 | AED 2.5m | — | — |
| 8 Jan 2026 | Land Ready | 1,550 | AED 2.5m | — | — |
| 7 Jan 2026 | Land Ready | 1,539 | AED 2.5m | — | — |
| 13 Nov 2025 | Land Ready | 1,550 | AED 1.8m | — | — |
Every type of sale, newest first; DLD publishes no time of day. Price per sq ft for homes only. “vs area”: against the median for that size in Al Yelayiss 1, Oct 2025–Sep 2026.
None of DAMAC’s 39 running ads names DAMAC Islands - Bali 1; these are the newest, from Meta’s Ad Library on 26 Oct 2026. Prices and claims in ads are the developer’s, not checked against DLD records.

From dusk till dawn, the build never stops. At Safa Two, every shift brings new progress, with precision, expertise and teamwork shaping what comes next. #DAMAC #SafaTwo #ConstructionUpdate

A new wave of luxury living is taking shape on Dubai’s coastline. DAMAC Bay by Cavalli has reached 35% overall progress, with 65% of the superstructure complete and 15% of the facade now taking shape. As the vision rises, a new expression of coastal luxury draws closer to reality. #DAMAC #DAMACBayByCavalli #LuxuryLiving #ConstructionUpdate

Your new view is waiting. Introducing Sorrento Lagoon Views, with studios and 1-Bedroom apartments. #DAMAC #LuxuryLiving #SorrentoLagoonViews

50,000+ homes delivered, shaped by the relationships behind them. A few words from valued partners who have been part of the journey. #DAMAC #DAMAC50K #OneFamily
Registered with DLD under the district Al Yelayiss 1, 2019 to 5 Oct 2026.
Each point is the median price per square foot of the month’s registered home sales (flats and villas). A month with fewer than 10 home sales is left as a gap. Registered prices, not asking prices.
Most sold size
4 bedroom
Share of the home sales over Oct 2025–Sep 2026 that recorded a bedroom count
Sales a year
Full years only, registered sales of every type. 3,944 sales in 2026 to 5 Oct.
Off-plan share
81% of the 4,328 sales over Oct 2025–Sep 2026 were registered as off-plan, DLD’s own registration type.
| Year | Sales | Off-plan | Ready | Value | Median home price | Median AED /sq ft |
|---|---|---|---|---|---|---|
| 2025 | 295 | 0 | 295 | AED 845m | — | — |
| 2026 to 5 Oct | 9 | 0 | 9 | AED 28.5m | — | — |
Sales and value: registered sales of every property type since Jan 2019. Off-plan: DLD’s registration type; Ready: every other sale. Medians: home sales only, shown with 5 or more.
Every registered sale, all property types.
4,328 sales were registered in Al Yelayiss 1 over Oct 2025–Sep 2026, with homes at a median AED 1,744 per sq ft over Jul–Sep 2026.
| Project | Developer | DLD register | Sales, Oct 2025–Sep 2026 | Median home price |
|---|---|---|---|---|
| DAMAC Islands 2 - Bahamas 2 | DAMAC | Due Jun 2030 | 497 | AED 2.8m |
| DAMAC Islands 2 - Bahamas 1 | DAMAC | Due Jun 2030 | 476 | AED 2.9m |
| DAMAC Islands 2 - Cuba | DAMAC | Due Jun 2030 | 439 | AED 2.8m |
| DAMAC Islands 2 - Bermuda | DAMAC | Due Jun 2030 | 401 | AED 2.9m |
| DAMAC Islands 2 - Tahiti 2 | DAMAC | Due Jun 2030 | 378 | AED 2.9m |
| DAMAC Islands 2 - Maui | DAMAC | Due Jun 2030 | 347 | AED 2.9m |
| DAMAC Islands 2 - Barbados 1 | DAMAC | Due Jun 2030 | 318 | AED 2.9m |
| DAMAC Islands 2 - Barbados 2 | DAMAC | Due Jun 2030 | 271 | AED 2.9m |
| DAMAC Islands 2 - Tahiti 1 | DAMAC | Due Jun 2030 | 253 | AED 3.3m |
| DAMAC Islands - Seychelles 2 | DAMAC | Due Jun 2029 | 180 | — |
| DAMAC Islands 2 - Antigua 1 | DAMAC | Due Dec 2030 | 159 | AED 3.0m |
| DAMAC Islands - Bali 3 | DAMAC | Due Jun 2029 | 56 | — |
Median home price over Oct 2025–Sep 2026, shown with 5 or more home sales.
| Project | Area | Completion date | Built | Sales, Oct 2025–Sep 2026 |
|---|---|---|---|---|
| DAMAC Lagoons - Valencia | Al Hebiah Fifth | Feb 2028 | 5.2% | 1,278 |
| DAMAC District | DAMAC Hills | Mar 2029 | 4.1% | 705 |
| DAMAC Riverside Views - Azure 2 | Dubai Investment Park Second | Mar 2029 | 5.8% | 692 |
| DAMAC Riverside Views - Capri 1 | Dubai Investment Park Second | Mar 2029 | 8.2% | 638 |
| DAMAC Lagoons - Lagoon Views 13 | Al Hebiah Fifth | Dec 2027 | 6% | 525 |
| DAMAC Islands 2 - Bahamas 2 | Al Yelayiss 1 | Jun 2030 | 0.3% | 497 |
| DAMAC Islands 2 - Bahamas 1 | Al Yelayiss 1 | Jun 2030 | 0.3% | 476 |
| DAMAC Islands 2 - Cuba | Al Yelayiss 1 | Jun 2030 | 0.2% | 439 |
| DAMAC Islands 2 - Bermuda | Al Yelayiss 1 | Jun 2030 | 0.2% | 401 |
| Chelsea Residences 2 by DAMAC | Dubai Maritime City | Dec 2029 | 5.4% | 394 |
| DAMAC Islands 2 - Tahiti 2 | Al Yelayiss 1 | Jun 2030 | 0.3% | 378 |
| DAMAC Islands 2 - Maui | Al Yelayiss 1 | Jun 2030 | 0.2% | 347 |
Al Hebiah Fifth · DAMAC
DAMAC Hills · DAMAC
Dubai Investment Park Second · DAMAC
Dubai Investment Park Second · DAMAC
Al Hebiah Fifth · DAMAC
Al Yelayiss 1 · DAMAC
Photos: Towers under construction, Dubai by Leandro Neumann Ciuffo (Wikimedia Commons, CC BY 2.0); Dubai Motor City by أمين علوان (Wikimedia Commons, CC BY-SA 4.0); Sheikh Zayed Road from above by monicker (Wikimedia Commons, CC BY-SA 3.0). Resized and cropped.
Al Yelayiss 1 · DAMAC
Al Yelayiss 1 · DAMAC
Al Yelayiss 1 · DAMAC
Al Yelayiss 1 · DAMAC
Al Yelayiss 1 · DAMAC
Al Yelayiss 1 · DAMAC
Photos: Towers in Business Bay by giggel (Wikimedia Commons, CC BY 3.0); Sheikh Zayed Road from above by monicker (Wikimedia Commons, CC BY-SA 3.0); Towers under construction, Dubai by Leandro Neumann Ciuffo (Wikimedia Commons, CC BY 2.0). Resized and cropped.
DAMAC Islands - Bali 1 is a DAMAC project in Al Yelayiss 1, Dubai, registered with the Dubai Land Department as project 3475 by Damac Elite Investment Co. L.L.C. The register lists it as active, with a completion date of 31 Dec 2028, 2.79% built at DLD’s inspection on 4 May 2026.
304 sales have been registered since Jan 2019, the first on 17 Feb 2025, 16 of them over Oct 2025–Sep 2026. The sales include 304 land plots, left out of every price figure. These are prices buyers paid, recorded at registration, not asking prices.
By sales since Jan 2019 it is 22nd of the 37 projects with a registered sale in Al Yelayiss 1, and 112th of DAMAC’s 255.
The DLD register lists a completion date of 31 Dec 2028. It was 2.79% built at DLD’s inspection on 4 May 2026. These are the register’s own figures, read 13 Oct 2026; we don’t forecast a finish.
No. The DLD register lists it as active, 2.79% built at the inspection on 4 May 2026.
304 sales registered with the Dubai Land Department since Jan 2019, 16 of them over Oct 2025–Sep 2026. The count includes 304 land plots, which are left out of every price figure.
The DLD register lists Damac Elite Investment Co. L.L.C, DLD developer number 2035, which we group under DAMAC.
In Al Yelayiss 1, Dubai. The Dubai Land Department registers its sales under the district Al Yelayiss 1. Homes there registered at a median AED 1,744 per sq ft over Jul–Sep 2026.
The DLD project register lists an escrow account with Emirates Nbd Bank () for DAMAC Islands - Bali 1.
Cite this page
DAMAC Islands - Bali 1, Al Yelayiss 1. Real Estate IQ, from DLD registered sales to 5 Oct 2026 and the DLD project register read 13 Oct 2026. dubairealestateiq.com/project/damac-islands-bali-1
Sources: Dubai Land Department open data, registered sales to 5 Oct 2026, via Dubai Real Estate Data (CC BY 4.0), processed by Real Estate IQ; DLD project register, read 13 Oct 2026. Registered prices, not asking prices or valuations. How the figures are worked out.
GuideHow to check a Dubai off-plan project’s completion date
GuideAsking price or registered price: how to check a quote
TrackerActive projects on the DLD register, with their completion datesPhotos: Towers under construction, Dubai by Leandro Neumann Ciuffo (Wikimedia Commons, CC BY 2.0); Dubai Marina at night by Gfilip (Wikimedia Commons, CC BY-SA 4.0); Dubai skyline at dusk by imran shahabuddin (Wikimedia Commons, CC BY 2.0). Resized and cropped.